The critical path

Identify the critical path as the longest path through the activity network; determine the minimum project completion time; interpret the effect of delays to critical and non-critical activities.

Worked examples

Identifying the critical path

Moderate

Problem

A project has the following activities. Find the minimum completion time and identify the critical path.
ActivityPredecessorsDuration (days)
A—5
B—3
CA4
DA, B6
EC, D3

Effect of a delay on a critical activity

Moderate

Problem

Using the project above (critical path A → D → E, minimum completion time 14 days), activity D is delayed by 4 days. What is the new minimum completion time?

Effect of a delay on a non-critical activity

Challenging

Problem

Activity B (float = 2 days) is delayed by 5 days. By how many days is the project delayed?

Practise

Q1·Straightforward
An activity has an earliest start time (EST) of 4 days and a latest start time (LST) of 4 days. What is the float of this activity?

Float = LST − EST.
Q2·Straightforward
A project has the following activities with durations (in days):
ActivityPredecessorsDuration
A—5
BA3
CA6
DB, C4
The minimum completion time of the project is the EFT of the last activity. Perform a forward scan and find the minimum completion time.
Q3·Straightforward
Which statement correctly describes the critical path in a project network?
Q4·Moderate
A project has the following activities:
ActivityPredecessorsDuration (days)
A—3
B—7
CA5
DA, B2
EC, D4
Perform a forward scan and find the minimum project completion time.
Q5·Moderate
Using the same project as the previous question (minimum completion time = 13 days):
ActivityPredecessorsDuration (days)
A—3
B—7
CA5
DA, B2
EC, D4
After completing a forward and backward scan, the float values are:
- A: float = 4, B: float = 0, C: float = 4, D: float = 0, E: float = 0

How many activities are on the critical path?
Q6·Moderate
A project has minimum completion time of 20 days. Activity G is on the critical path and has a duration of 3 days. If activity G is delayed by 2 days, what is the new minimum project completion time (in days)?
Q7·Moderate
Activity H has float of 5 days. If activity H is delayed by 3 days, by how many days is the project completion time extended?
Q8·Moderate
A project has the following activities:
ActivityPredecessorsDuration (days)
A—4
B—2
CA3
DB6
EC, D5
The critical path runs through A → C → E or B → D → E. Determine the minimum project completion time.
Q9·Challenging
A project has the following activities:
ActivityPredecessorsDuration (days)
A—2
B—5
CA4
DA, B3
EC6
FD, E2
Perform a complete forward scan and find the minimum project completion time.
Q10·Challenging
Using the same project as the previous question (minimum completion time = 14 days):
ActivityPredecessorsDuration (days)
A—2
B—5
CA4
DA, B3
EC6
FD, E2
Perform a backward scan. What is the float of activity B?
Q11·Challenging
Using the same project (completion time = 14 days):
ActivityPredecessorsDuration (days)
A—2
B—5
CA4
DA, B3
EC6
FD, E2
Activity B has float of 4 days. If activity B is delayed by 5 days, by how many days is the minimum project completion time extended?
Q12·Challenging
A project has the following activities:
ActivityPredecessorsDuration (days)
A—6
B—4
CA3
DA, B5
EB8
FC, D2
GE, F1
Find the minimum project completion time.